A question came up regarding a cost code and the open commitment it had $44,844.10 open commitment. When I drilled into the cost code, only one PO showed up for $1,179.60. When I drilled into the PO, it agreed to the $1,179.60. Does anyone know what else can contribute to $44.8k open commitment and how I can find it.
↧